Obtaining a Building
Permit
Permits are required for most
construction activities including moving or demolishing a
structure. The permit process gives the City the opportunity to
determine if the construction meets the requirements of the
Building Ordinance as well to ensure that the use of the
property is consistent with surrounding uses and the City Zoning
Ordinance. No building is to be constructed, reconstructed,
remodeled, erected, altered, enlarged, repaired, moved or
demolished, or have ground broken up for construction without a
building permit issued by the City.
Download Building & Zoning Permit
Application.
Other Permits
Airport Zoning Permit. A
permit is required for any proposed structure 35 feet or higher
within 3 miles of the airport.
Download Airport Zoning Permit
Application.
Sewer and Water
Connection/Disconnect. A Utility Permit is required for any
connection or disconnection to a water or sewer main.
Additionally, any repair to the sewer lateral serving a specific
property requires a permit. Permits can be obtained by
contacting Julie Jackson, Municipal Technician, at City Hall at
(608) 326-8024 or
pdcjack@mhtc.net.
Street Opening. A Utility
Permit
is required to cut a street curb for such things as installation
of a driveway or to open a street for such things as repair of a
sewer or water line. Permits can be obtained by contacting Julie
Jackson, Municipal Technician, at City Hall at (608) 326-8024 or
pdcjack@mhtc.net.
Signs. A permit is
generally required for installation of any sign. There are
exceptions to this rule, and it is a good idea to check ahead of
time with City staff.
Download Sign Permit Application.
Rezoning
All land in the City of Prairie
du Chien is designated to one of ten zoning districts specified
in the Zoning Ordinance. Additionally, there are two floodplain
overlay districts. Certain land uses are allowed in each zoning
district, and the regulations governing each district vary. The
process of changing a parcel’s zoning is called a rezoning.
A rezoning application will be
evaluated based upon the proposed zone’s compatibility with
existing zoning districts, surrounding uses, consistency with
the City’s Comprehensive Plan, and potential impacts of the
proposed zoning district.
Download Rezoning Application.
Conditional Use Permit
The City of Prairie du Chien
Zoning Ordinance allows certain land uses in each zoning
district. Some uses are generally permitted in each district.
However, some land uses require the issuance of a Conditional
Use Permit by the City Plan Commission. A conditional use
application will be evaluated based upon the proposed use’s
compatibility with surrounding zoning and uses and consistency
with the City’s Comprehensive Plan.
The City Plan Commission may make
approval contingent on certain “conditions” being met.
Requirements may include such things as landscaping,
architectural design, type of construction, construction
commencement and completion dates, sureties, lighting, fencing,
planting screens, operational control, hours of operation,
improved traffic circulation, time period of permit, deed
restrictions, highway access restrictions, increased yards, and
parking.
Download Conditional Use Permit
Application.
Variance
A variance is a relaxation to the
terms or requirements of the Zoning Ordinance. A variance cannot
relax the list of permitted and conditional land uses within a
zoning district. A variance may be granted when conditions are
unique to the property and not the result of the applicant’s
actions. The applicant must show a demonstrable hardship that
unreasonably restricts the use of the property.
Download Variance Application.